Failed ERP implementation will change partners to become trusted advisors.

A norwegian customer won a compensation case against an ERP implementation partner after the customer terminated the parties’ agreement on the supply of a new ERP. The customer was compensated by the Norwegian district court assessed at 288 mNOK (36,7 mUSD). Originally the contract was worth 120 mNOK. You can read the complete story here http://www.selmer.no/en/nyhet/felleskjopet-agri-wins-district-court-case. The court decision is expected to be appealed.

Luckily this was NOT a Dynamics 365 implementation, and the customer is actually replacing the failed ERP system with Dynamics 365. The reason why I wanted to write about this story is that it has implications on how much risk and responsibility an ERP implementation partner can take. A major part of the ERP partners are smaller companies with less than 100 employees, than cannot take the risk of getting into such a situation. There are always problems and risks that is beyond what a ERP partner can control. Partners are not the developer company of the standard software. They are implementing, and in some cases adding additional extensions. Also the cloud based software are running on azure that is beyond the control of the partner.

How can this change partners behavior? Partners are changing towards becoming verticalized trusted advisors, but with limited responsibilities. We can give recommendations based on what we know about the software and how to use it efficiently but the costs are more on a T&M(Time and Material) basis. It will more be the customer them selves that is responsible for the implementation and time-tables.

Some customers will not accept this change, but other do. There are currently resource constrains in the Dynamics 365 partner channel and we partners avoiding customers that takes a back-seat approach towards their implementation projects. The sales focus will change towards those customers that take more of the responsibility themselves, and that do understand to take a more dynamic and agile approach. A 400-page requirement document is not a good start for an ERP project, as we see the digitalization possibilities are accelerating. We also see that customers don’t run a 2 year ERP implementation project before going live. They run a 90 days project to get live with only parts of their requirements. The project then takes on other areas and they extend their use of the Dynamics 365.

At the end, I include some trusted advisor recommendations that I think can inspire anyone that is about to start a project.

I appreciate that I can be a part of this worldwide blog community—as a consultant working from Norway, the blog lets me share more than 20 years of experience with Microsoft Dynamics 365. Along the way, I participated in developing retail, PDA/RF, barcoding, master data, kitting and WMS-solutions for Dynamics. My blog focuses on my deepest interests and expertise: along with a 360 degree view of digital transformation topics, I welcome opportunities to dive into retail and intercompany supply chain automation, logistics, and production—everything that is moving around in a truly connected enterprise. As Enterprise Architect on Dynamics 365, I specialize in strategic development and planning for corporate vertical solutions and works to build international networks that increase knowledge and understanding for Dynamics 365. As an advocate for both providers and customers, I'm committed to ensure that customers constantly changing needs are meet, and I see community as key for increasing expertise. I welcome you to connect with me.

4 comments on “Failed ERP implementation will change partners to become trusted advisors.

  1. Josip Gracak

    Agree with the post however careful with putting “Quality” as the last point as that might be the downfall of the whole project.

    Like

    • I agree that quality is important, but there are many levels on that from perfect to “good enough”. If quality issues are too severe, then the project delivery is not performed. MVP (minimum viable product) is a concept I like, and see it on the following video on this : https://www.youtube.com/watch?v=0P7nCmln7PM

      Like

      • Josip Gracak

        Agree, it’s about building a minimum viable product while at the same time thinking of the long term goal of the client and not jeopardizing future upgrades or maintainability of the solution. In ERP terms it’s usually postponing things to different “business releases” instead of trying to cram all requirements into a big bang.

        Liked by 1 person

  2. Ole Jensen

    Hi Kurt, 100% agree with this blog post. It might be win-win for both customer and partner to do an fast & agile time and material based implementation in stead of the traditional fixed price waterfall approach.Better to focus on setting up and working with functionality in the new ERP – not on producing big analysis reports about how things was in the old ERP.

    Like

Leave a Reply to Kurt Hatlevik Cancel reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

%d bloggers like this: